Impact of Loader Size on Dowtime Generation in Primary Crushing Plant
Abstract: Feeding plant is the first parameter while you are studying plant performance. During feeding process in a crushing circuit, reduction of downtime is one of the most important key because it is optimising circuit and by the way increasing significantly feeding, production and profitability of the plant. In this article, we are going to compare three types of loader used to feed a crushing plant of 250tph capacity.10tons loader was found the best based on the parameters monitored.
Keywords: Downtime, running time, loaders, feed, primary crushing plant
How to Cite?: Ngwanza Saluzoludiey Hugues, Kayombo Ilunga Patrick, "Impact of Loader Size on Dowtime Generation in Primary Crushing Plant", Volume 7 Issue 6, June 2018, International Journal of Science and Research (IJSR), Pages: 1510-1514, https://www.ijsr.net/getabstract.php?paperid=ART20183234, DOI: https://dx.doi.org/10.21275/ART20183234