Multiple Resource Leveling using Re-Modified Minimum Moment Method to Construction Project

Lokendra Magendra | Sudhanshu Pathak


Abstract: A Project Manager frequently comes across two types of situations time constraints and resource constraints. A project requires resource to execute the activities. These resources include labor, equipment and materials required to complete the work. In the ideal world, resources are unlimited but in the real world they are generally not unlimited and the project team needs to level out the consumption of resource. The purpose of this paper is to apply Re-modified minimum moment method for multiple resource leveling to a construction project and resource leveling by using primavera project management software for the same project and to determine the optimum solution. The method is based on critical path method. To achieve the objective, data of construction of a residential tower is taken. It has been observed that Re-modification minimum moment gives optimum solution than primavera software.


Keywords: Resource rate, Resource Leveling, Re-Modified Minimum Moment Method, Primavera


Edition: Volume 5 Issue 6, June 2016,


Pages: 332 - 335


How to Download this Article?

You Need to Register Your Email Address Before You Can Download the Article PDF


How to Cite this Article?

Lokendra Magendra, Sudhanshu Pathak, "Multiple Resource Leveling using Re-Modified Minimum Moment Method to Construction Project", International Journal of Science and Research (IJSR), Volume 5 Issue 6, June 2016, pp. 332-335, https://www.ijsr.net/get_abstract.php?paper_id=NOV164011

Similar Articles with Keyword 'Primavera'

Downloads: 134

Research Paper, Civil Engineering, India, Volume 6 Issue 3, March 2017

Pages: 658 - 662

Work Breakdown Structure Scheduling for Repetitive Construction Projects with Soft Logics

Lekshmi A L | Dr. T R Sethu Raman | Sreeja V [2]

Share this Article

Downloads: 176

Research Paper, Civil Engineering, India, Volume 4 Issue 8, August 2015

Pages: 422 - 425

Time and Cost Planning in Construction Project

Sandip Pawar | P. M. Attarde

Share this Article
Top